Software Engineering MCQs for job test and interview preparation, especially for fresh graduates, students, and candidates appearing in competitive exams. These multiple-choice questions cover a wide range of topics, including the fundamentals of software engineering, its various types, advanced concepts, software design, development processes, testing methods, software evolution, and security aspects.

COCOMO stands for____________________?

A Constructive cost model
B Comprehensive cost model
C Constructive cost estimation model
D Complete cost estimation model
Correct Answer: Constructive cost model

Which one is not a risk management activity ?

A Risk assessment
B Risk generation
C Risk control
D None of the mentioned
Correct Answer: Risk generation

Which of the following uses empirically derived formulas to predict effort as a function of LOC or FP ?

A FP-Based Estimation
B Process-Based Estimation
C COCOMO
D Both FP-Based Estimation and COCOMO
Correct Answer: FP-Based Estimation

Which version of COCOMO states that once requirements have been stabilized, the basic software architecture has been established ?

A Early design stage model
B Post-architecture-stage model
C Application composition model
D All of the mentioned
Correct Answer: Early design stage model

Which model was used during the early stages of software engineering, when prototyping of user interfaces, consideration of software and system interaction, assessment of performance, and evaluation of technology maturity were paramount ?

A Early design stage model
B Post-architecture-stage model
C Application composition model
D All of the mentioned
Correct Answer: Application composition model

COCOMO was developed initially by _____________________ ?

A B.Beizer
B Rajiv Gupta
C B.W.Bohem
D Gregg Rothermal
Correct Answer: B.W.Bohem

COCOMO-II was developed at _____________________?

A University of Texas
B University of Southern California
C MIT
D IIT-Kanpur
Correct Answer: University of Southern California

What all has to be identified as per risk identification ?

A Threats
B Vulnerabilities
C Consequences
D All of the mentioned
Correct Answer: All of the mentioned

Which one is not a size measure for software product ?

A LOC
B Halstead’s program length
C Function Count
D Cyclomatic Complexity
Correct Answer: Cyclomatic Complexity

Estimation of size for a project is dependent on___________________?

A Cost
B Time
C Schedule
D None of the mentioned
Correct Answer: None of the mentioned